Many netizens who are currently refurbishing are busy purchasing building materials and furniture. Some netizens think that buying in advance will save time or setting up building materials for business promotion. In fact, many building materials and furniture must be matched with the decoration process, or the construction of a certain degree to the specific model, communicate with the designer in advance, otherwise it will bring the late and the entire decoration style does not match or because of the need to change the model or Returns, affect the home improvement process. Aijia designers have formulated a detailed timetable for purchasing building materials. They hope to bring inspiration and reminders to your home decoration.
Can be purchased before the start of construction1, heating:
Since the floor heating requires four to five days of construction, and the fitting-out works cannot be carried out during the construction of the floor heating, it is recommended that the owners who know more about the floor heating products can complete the floor heating construction before the renovation, which will save time.
2, cabinets:
Mainly the design of functional zoning, the initial need to set the cabinet manufacturers before the hydropower reform, so that manufacturers to conduct preliminary measurements to determine the location of the cabinet, the use of the way and the location of electrical and water circuits. After the tiles are finished, the cabinet manufacturers make the second measurement. At this time, they communicate with the designer to determine the cabinet color patterns and various methods.
Recommended purchase time: before the start of hydropower reform.
3, heating:
If the room structure or area changes, the required number of radiators will change accordingly. Therefore, the previous custom heating is not consistent with the needs of the entire room.
Recommended purchase time: After the design plan is confirmed.